Generator transformers installed at Akkuyu NPP Unit 1

Generator transformers installed at Akkuyu NPP Unit 1

One of the key stages in connecting the unit to Türkiye's national power grid completed
Press release
Photo

February 03, 2026, Büyükeceli, Mersin Province, Türkiye. – The transportation and installation of the step-up generator transformers into the design positions has been completed at Akkuyu NPP (being built by Rosatom State Corporation) construction site. The equipment was transported from a storage area and installed on specially prepared foundations.

"Step-up transformers are one of the key components of a power unit's power output system. They transmit electricity generated by the turbine generator to the integrated switchgear and then to the interconnected grid of the Republic of Türkiye. The transformers are equipped with advanced protection systems and special switching devices that allow for smooth voltage adjustments", Akkuyu Nuclear JSC Chief Executive Officer Sergei Butckikh noted.

Currently, with the participation of the manufacturer's experts, work is underway on the transformers to install high-voltage bushings, cooling systems, as well as control and monitoring systems.

Installation of the transformers has become an important step in preparing the power unit for subsequent operations on connecting power equipment, conducting high-voltage tests, and developing the Akkuyu NPP power output system.

About generator transformers

Step-up generator transformers are designed to convert 24 kilovolts (kV) generated by the turbine generator to 400 kV grid voltage. They transmit electricity from the generator to the gas insulated switchgear (GIS). Each power unit includes four single-phase generator transformers: three operating transformers and one standby transformer. Each transformer weighs 283 tons, excluding consumed oil.

The equipment was manufactured in Russia by Nevsky Transformer JSC (Saint Petersburg). The step-up generator transformers have a capacity of 533,000 kVA each and are equipped with an air-cooling system and an on-load tap changer.

Prior to rigging, preparatory work was completed on site, including laying foundations, installing grounding, constructing fire barriers and civil structures of 24 and 400 kV bus ducts, as well as installing fire extinguishing systems.

At the next stage, auxiliary equipment will be installed in the transformer installation area. Busbars will be connected, and control, protection, and automatic fire extinguishing systems will be installed and commissioned. Prior to connection, the transformers will undergo a series of high-voltage tests.


About Akkuyu NPP

Akkuyu NPP is the first-ever nuclear power plant in the Republic of Türkiye being built by Rosatom. The Akkuyu NPP project includes four power units equipped with Generation 3+ VVER reactors of Russian design. The capacity of each NPP power unit will be 1200 MW.

Akkuyu NPP is the first project in the global nuclear industry being implemented according to the Build-Own-Operate model.

Russia is developing cooperation with all interested countries. Implementation of major international projects is going on. Rosatom and its divisions take part in this work.